NMDOT CN - S100311 SANTA FE COUNTY, NINE MILE BRIDGE OVER 1-25 - BRIDGE REHAB/RAISING
Contract Type - Prime Contract
NMDOT Contact: Thomas Griego, District Construction Engineer, (505)231-2864
Contract Amount: $673,480.42
Contract Date: July 1, 2015
Substantial Completion: December, 2015
Epoxy Overlay Completed: June 2016
Project Scope:
Bridge Rehabilitation, Raise Bridge 8", Replace Bearings, Epoxy Overlay
Major Contract Items:
-
Raising Bridge, Replacing Bearings
-
HPD Concrete, Replace Overhamgs
-
Deck Repairs
-
Pier and Abutment Repairs
-
Asphalt Paving Approaches
-
Backwall Repairs
-
Epoxy Deck Overlay
VCG worked closely with NMDOT to re-phase the project and complete all major work without interruption to local traffic. Bridge Raising was planned with live traffic loads on bridge to allow local traffic to cross bridge.