NMDOT CN - S100311 SANTA FE COUNTY, NINE MILE BRIDGE OVER 1-25 - BRIDGE REHAB/RAISING

Contract Type - Prime Contract

​

NMDOT Contact: Thomas Griego, District Construction Engineer, (505)231-2864

​

Contract Amount: $673,480.42

Contract Date: July 1, 2015

Substantial Completion: December, 2015

Epoxy Overlay Completed: June 2016

​

Project Scope:

Bridge Rehabilitation, Raise Bridge 8", Replace Bearings, Epoxy Overlay

​

Major Contract Items:

  • Raising Bridge, Replacing Bearings

  • HPD Concrete, Replace Overhamgs

  • Deck Repairs

  • Pier and Abutment Repairs

  • Asphalt Paving Approaches

  • Backwall Repairs

  • Epoxy Deck Overlay

​

VCG worked closely with NMDOT to re-phase the project and complete all major work without interruption to local traffic. Bridge Raising was planned with live traffic loads on bridge to allow local traffic to cross bridge.