top of page

ISLETA DRAIN DIVERSION STRUCTURES - AMAFCA

Contract Type - Prime Contract

AMAFCA PM: Brad Bingham, Project Manager, (505)238-1277

Final Contract Amount: $1,012,852.78

Original Contract: $849,412.00

Contract Date: October 5, 2016

Substantial Completion: March 21, 2017

Project Scope:

Major Drain Flood Control Structure for Isleta Drain & Pajarito Crossing

Major Contract Items:

  • Structural Concrete

  • 84" Reinforced Concrete Pipe

  • 76" Corrugated Metal Pipe

  • Orifice Wall / Inlet with Grates

  • Weir Inlet with Grates

  • Excavation/ Prewetting and Compaction

  • Dewatering

  • Traffic Control

  • Fencing

  • Major Change included 16" DIP Waterline relocation under the structure. Designed and Constructed 160' waterline relocation in 21 days. 

bottom of page