ISLETA DRAIN DIVERSION STRUCTURES - AMAFCA
Contract Type - Prime Contract
AMAFCA PM: Brad Bingham, Project Manager, (505)238-1277
Final Contract Amount: $1,012,852.78
Original Contract: $849,412.00
Contract Date: October 5, 2016
Substantial Completion: March 21, 2017
Project Scope:
Major Drain Flood Control Structure for Isleta Drain & Pajarito Crossing
Major Contract Items:
-
Structural Concrete
-
84" Reinforced Concrete Pipe
-
76" Corrugated Metal Pipe
-
Orifice Wall / Inlet with Grates
-
Weir Inlet with Grates
-
Excavation/ Prewetting and Compaction
-
Dewatering
-
Traffic Control
-
Fencing
-
Major Change included 16" DIP Waterline relocation under the structure. Designed and Constructed 160' waterline relocation in 21 days.