NMDOT CN - 4100320 SAN MIGUEL COUNTY

Contract Type - Prime Contract

NMDOT Contact: David, Project Manager, (505)629-7294

Contract Amount: $4,999,725.00

Contract Date: January 4, 2017

As of August 1, 2017: 52% Complete

Project Scope:

Replacement of 2 bridges on NM 104  in San Miguel County

Major Contract Items:

  • Drilled Shafts

  • Structural Concrete

  • Bridge Beams

  • Asphalt Paving

  • Excavation / Borrow

  • Detour Construction

  • Temporary Bridge Structure Provided and Maintained by Contractor

  • Drainage Structures

  • Traffic Control

  • Temporary Shoring of Existing Bridge