ARA PECOS - RDAM WALL TESTING - APPLIED RESEARCH ASSOCIATES, INC.

Contract Type - Prime Subcontract

Contact: Jeff Fisher, PE, Project Manager, (850)774-2475

Contract Amount: $95,000.95

Contract Date: May 1, 2015

Project Completed: July, 2015

Project Scope:

Erected 4 section of T-Walls for Blast Testing, Remove and Dispose of T-Walls after testing

Major Contract Items:

  • Subgrade Preparation

  • Erect T-Walls, Install Anchor Bolts

  • Install Cross Tie Bolts

  • Remove T-Walls from 4 Locations

  • Dispose of T-Walls

VCG executed the Schedule in 1/2 the planned time, coordinated pre-cast operations and value engineered the disposal process onsite after blast testing