ARA PECOS - RDAM WALL TESTING - APPLIED RESEARCH ASSOCIATES, INC.
Contract Type - Prime Subcontract
Contact: Jeff Fisher, PE, Project Manager, (850)774-2475
Contract Amount: $95,000.95
Contract Date: May 1, 2015
Project Completed: July, 2015
Project Scope:
Erected 4 section of T-Walls for Blast Testing, Remove and Dispose of T-Walls after testing
Major Contract Items:
-
Subgrade Preparation
-
Erect T-Walls, Install Anchor Bolts
-
Install Cross Tie Bolts
-
Remove T-Walls from 4 Locations
-
Dispose of T-Walls
VCG executed the Schedule in 1/2 the planned time, coordinated pre-cast operations and value engineered the disposal process onsite after blast testing